Here's the thing about concrete floors—somebody always has to tie that bottom layer. It's slow, it's hard on the back, and by row nine nobody's checking row nine anymore. A welded rebar truss doesn't make tying faster. It just moves the whole job to a factory. The cage shows up already welded—top chord, two bottom chords, bent web bars—set to the right depth. Guys on site lay panels and pour. That's it.

The numbers are pretty ordinary. Heights from 70 to 270 mm. Bars mostly 4 to 12 mm. Base sheet 576 or 600 wide, 0.4–0.8 thick, galvanized or cold-rolled. Slabs 100 to 300 mm. The one that usually decides things is unpropped span—call it 4.8 to 5 meters, against maybe 3 for plain open deck.

Item Typical Range
Truss height 70–270 mm
Top / bottom chord 6–12 mm
Web bar 4–8 mm
Base sheet width 576 / 600 mm
Base sheet thickness 0.4–0.8 mm
Slab depth 100–300 mm
Unpropped span up to ~4.8–5.0 m
Steel grade HRB400 / CRB550 equivalent

Steel rebar truss.jpg

Where do you actually see these? High-rise offices, mostly. One job in Fujian came in at 4.2 mm deflection when the limit was 24. Finished about 20% quicker, used half the formwork, and landed roughly 15% under budget. I wouldn't promise those numbers on your project, but that's the pattern—less labor on the deck, fewer props, faster turnover.

Schools too. A Shenzhen school with a non-removable cementitious truss deck went from three or four days of template work to under one. Tying dropped by more than half. Picked up about two weeks on the schedule. Again, not a law of physics, just what happened.

The one that surprised me was a pitched roof. Financial center, 38-degree slope, welded truss deck instead of formwork. 12.95 tonnes of rebar versus 81 tonnes the old way. No scaffolding on the slope at all. That's a lot of people who didn't have to work at height.

Bridges are their own story. There was a 60-meter composite span on Georgia's E60 Highway that got studied during construction. More trusses in the precast bottom slab meant less peak stress during lifting and less sag after the pour. The truss was earning its keep before the concrete even cured.

Data centers might be the most natural home for this stuff. One computing center used close to 20,000 square meters. Flat soffit means cable trays and ducts fit underneath—try that with a profiled deck and you're trapping services between ribs. Warehouses, electronics plants, mezzanines—same deal. Big plates, heavy loads, no time to prop and strip. A depot project in Hangzhou used truss panels across housing, a school, and community buildings, mostly because panels arrive done and the floor cycle doesn't depend on whether a tying crew is free.

Steel truss.jpg

Fire has been tested. 100 mm slab, 70 mm truss, 1.68-hour rating, chords fully encased. Stiffness in both directions stays within 5%, so it acts more like cast-in-place than a one-way deck. There's some bridge literature about fatigue on welded joints—general takeaway is the permanent bars carry the load even if a temporary weld gives up, so the truss isn't the only tension path.

And yeah, it costs more per square meter than plain open profile. No point pretending otherwise. The case is what you don't pay for: tying labor, prop rental, slow floor cycles. On a labor-short high-rise or a job with a hard deadline, those three usually win before anybody opens a spreadsheet. Cantilevers and weird floor plates can work, but they push you to thicker chords or extra support, and the unpropped advantage shrinks out at the edges.

Inside its lane, a rebar truss deck does one job well—takes a field operation and puts it in a plant, so the deck just gets laid and poured. The right projects tend to announce themselves: live space underneath, no room for props, a schedule that can't wait on tying crews, or a slab shape that makes normal formwork a pain.

Contact Us for More Information